BetaActiveSolarBatteryPacifiCorpLBNL
300 MW hybrid in Klamath, OR · In queue since May 2021 · Proposed COD December 2025
300 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 7m
Schedule
4 months past proposed COD
Construction75%
Queue EntryMay 7, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
OR
County
Klamath
Region
West
Developer
Sugar Pine Solar Project LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Chiloquin-LaPine transmission line
Data Source
LBNL
No news available for this project.