BetaActiveBatteryPacifiCorpLBNL
2.3 MW storage in Klamath, OR · In queue since May 2021 · Proposed COD February 2023
2.3 MW
Capacity
1
Components
Battery
4y 10m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 9m
Schedule
38 months past proposed COD
Construction75%
Queue EntryMay 5, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2023-02-01
Project Details
State
OR
County
Klamath
Region
West
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit 5L49 out of Lakeport substation
Data Source
LBNL
No news available for this project.