120 MW hybrid in Emery, UT · In queue since April 2021 · Proposed COD November 2024
120 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 7m
Schedule
16 months past proposed COD
Facilities Study50%
Queue EntryApr 21, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-30
Project Details
State
UT
County
Emery
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Emery-Sigurd #2 transmission line
Data Source
LBNL