— Project Summary

Queue ID
PacifiCorp-C1-10
Capacity
45 MW
Technology
Solar+Battery
Status
active
Location
Emery, UT
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryPacifiCorpLBNL

45 MW hybrid in Emery, UT · In queue since April 2021 · Proposed COD November 2024

45 MW

Capacity

1

Components

Solar

4y 11m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 7m

Schedule

16 months past proposed COD

Facilities Study50%
Queue EntryApr 21, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-11-30

Project Details

State

UT

County

Emery

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Moore substation

Data Source

LBNL

No news available for this project.