— Project Summary

Queue ID
PacifiCorp-C013
Capacity
326.25 MW
Technology
Wind
Status
active
Location
Meagher, MT
Region
West
Developer
IA Status

BetaActiveWindPacifiCorpLBNL

326.25 MW generation in Meagher, MT · In queue since January 2021 · Proposed COD December 2024

326.25 MW

Capacity

1

Components

Wind

5y 2m

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 11m

Schedule

15 months past proposed COD

Pre-Study0%
Queue EntryJan 28, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

MT

County

Meagher

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Loco Mountain substation

Data Source

LBNL

No news available for this project.