BetaActiveWindPacifiCorpLBNL
326.25 MW generation in Meagher, MT · In queue since January 2021 · Proposed COD December 2024
326.25 MW
Capacity
1
Components
Wind
5y 2m
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 11m
Schedule
15 months past proposed COD
Pre-Study0%
Queue EntryJan 28, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
MT
County
Meagher
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Loco Mountain substation
Data Source
LBNL
No news available for this project.