— Project Summary

Queue ID
PacifiCorp-C007
Capacity
300.15 MW
Technology
Wind
Status
active
Location
Meagher, MT
Region
West
Developer
IA Status

BetaActiveWindPacifiCorpLBNL

300.15 MW generation in Meagher, MT · In queue since March 2019 · Proposed COD October 2022

300.15 MW

Capacity

1

Components

Wind

7 years

In Queue

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 7m

Schedule

41 months past proposed COD

Pre-Study0%
Queue EntryMar 27, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-31

Project Details

State

MT

County

Meagher

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Loco Mountain substation

Data Source

LBNL

No news available for this project.