BetaActiveWindPacifiCorpLBNL
300.15 MW generation in Meagher, MT · In queue since March 2019 · Proposed COD October 2022
300.15 MW
Capacity
1
Components
Wind
7 years
In Queue
—
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 7m
Schedule
41 months past proposed COD
Pre-Study0%
Queue EntryMar 27, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-10-31
Project Details
State
MT
County
Meagher
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Loco Mountain substation
Data Source
LBNL
No news available for this project.