— Project Summary

Queue ID
PacifiCorp-C006
Capacity
600 MW
Technology
Wind
Status
active
Location
Wheatland, MT
Region
West
Developer
IA Status

BetaActiveWindPacifiCorpLBNL

600 MW generation in Wheatland, MT · In queue since February 2019 · Proposed COD December 2021

600 MW

Capacity

1

Components

Wind

7y 1m

In Queue

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

2y 10m

Schedule

52 months past proposed COD

Pre-Study0%
Queue EntryFeb 21, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

MT

County

Wheatland

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Loco Mountain substation

Data Source

LBNL

No news available for this project.