— Project Summary

Queue ID
PacifiCorp-C002
Capacity
450 MW
Technology
Battery
Status
suspended
Location
Meagher, MT
Region
West
Developer
IA Status

BetaSuspendedOther StoragePacifiCorpLBNL

450 MW storage in Meagher, MT · In queue since December 2016 · Proposed COD December 2020

450 MW

Capacity

1

Components

Other Storage

9y 3m

In Queue

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

4 years

Suspended0%
Queue EntryDec 5, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-12-30

Project Details

State

MT

County

Meagher

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Loco Mountain substation

Data Source

LBNL

No news available for this project.