0.41 MW generation in Franklin, ID · In queue since November 2017 · Proposed COD January 2018
0.41 MW
Capacity
1
Components
Hydro
8y 4m
In Queue
IA Executed
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2 months
Schedule
100 months past proposed COD
Construction75%
Queue EntryNov 14, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2018-01-01
Project Details
State
ID
County
Franklin
Region
West
Developer
City of Preston
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit PRS13 out of Preston substation
Data Source
LBNL