— Project Summary

Queue ID
PacifiCorp-958
Capacity
21.17 MW
Technology
Other
Status
suspended
Location
Lincoln, WY
Region
West
Developer
Ormat Nevada, Inc.
IA Status
Suspended

BetaSuspendedOtherPacifiCorpLBNL

21.17 MW generation in Lincoln, WY · In queue since October 2017 · Proposed COD February 2020

21.17 MW

Capacity

1

Components

Other

8y 5m

In Queue

Suspended

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

2y 4m

Suspended38%
Queue EntryOct 11, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-02-01

Project Details

State

WY

County

Lincoln

Region

West

Developer

Ormat Nevada, Inc.

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Lima substation

Data Source

LBNL