BetaSuspendedOtherPacifiCorpLBNL
21.17 MW generation in Lincoln, WY · In queue since October 2017 · Proposed COD February 2020
21.17 MW
Capacity
1
Components
Other
8y 5m
In Queue
Suspended
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
2y 4m
Suspended38%
Queue EntryOct 11, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-02-01
Project Details
State
WY
County
Lincoln
Region
West
Developer
Ormat Nevada, Inc.
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Lima substation
Data Source
LBNL