BetaSuspendedSolarPacifiCorpLBNL
80 MW generation in Yakima, WA · In queue since September 2017 · Proposed COD January 2020
80 MW
Capacity
1
Components
Solar
8y 6m
In Queue
Suspended
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
2y 4m
Suspended38%
Queue EntrySep 27, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-01-01
Project Details
State
WA
County
Yakima
Region
West
Developer
High Top Solar LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Union Gap - Midway transmission line
Data Source
LBNL