BetaSuspendedSolarBatteryPacifiCorpLBNL
50 MW hybrid in Klamath, OR · In queue since July 2017 · Proposed COD December 2019
50 MW
Capacity
1
Components
Solar
8y 8m
In Queue
IA Executed
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
2y 5m
Suspended75%
Queue EntryJul 12, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Proposed COD: 2019-12-01
Project Details
State
OR
County
Klamath
Region
West
Developer
Fresh Air Energy II, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Copco 2 - Westside Tap to Klamath Falls line (Line 18)
Data Source
LBNL
No news available for this project.