BetaSuspendedSolarBatteryPacifiCorpLBNL
45 MW hybrid in Box Elder, UT · In queue since April 2017 · Proposed COD June 2019
45 MW
Capacity
1
Components
Solar
8y 11m
In Queue
Suspended
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
2y 2m
Suspended38%
Queue EntryApr 6, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-06-30
Project Details
State
UT
County
Box Elder
Region
West
Developer
Rocket Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Lampo substation
Data Source
LBNL
No news available for this project.