BetaActiveSolarPacifiCorpLBNL
75 MW generation in Tooele, UT · In queue since January 2017 · Proposed COD June 2019
75 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
2y 5m
Schedule
82 months past proposed COD
Construction75%
Queue EntryJan 10, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2019-06-30
Project Details
State
UT
County
Tooele
Region
West
Developer
Horseshoe Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Horseshoe substation
Data Source
LBNL
No news available for this project.