— Project Summary

Queue ID
PacifiCorp-846
Capacity
75 MW
Technology
Solar
Status
active
Location
Tooele, UT
Region
West
Developer
Horseshoe Solar, LLC
IA Status
IA Executed

BetaActiveSolarPacifiCorpLBNL

75 MW generation in Tooele, UT · In queue since January 2017 · Proposed COD June 2019

75 MW

Capacity

1

Components

Solar

9y 2m

In Queue

IA Executed

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

2y 5m

Schedule

82 months past proposed COD

Construction75%
Queue EntryJan 10, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2019-06-30

Project Details

State

UT

County

Tooele

Region

West

Developer

Horseshoe Solar, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Horseshoe substation

Data Source

LBNL

No news available for this project.