— Project Summary

Queue ID
PacifiCorp-836
Capacity
400 MW
Technology
Wind
Status
active
Location
Carbon, WY
Region
West
Developer
PacifiCorp
IA Status
IA Executed

BetaActiveWindPacifiCorpLBNL

400 MW generation in Carbon, WY · In queue since December 2016 · Proposed COD October 2023

400 MW

Capacity

1

Components

Wind

9y 3m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

6y 10m

Schedule

30 months past proposed COD

Construction75%
Queue EntryDec 5, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2023-10-01

Project Details

State

WY

County

Carbon

Region

West

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Aeolus substation

Data Source

LBNL

No news available for this project.