BetaActiveWindPacifiCorpLBNL
400 MW generation in Carbon, WY · In queue since December 2016 · Proposed COD October 2023
400 MW
Capacity
1
Components
Wind
9y 3m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
6y 10m
Schedule
30 months past proposed COD
Construction75%
Queue EntryDec 5, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2023-10-01
Project Details
State
WY
County
Carbon
Region
West
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Aeolus substation
Data Source
LBNL
No news available for this project.