— Project Summary

Queue ID
PacifiCorp-823
Capacity
178 MW
Technology
Solar
Status
active
Location
Emery, UT
Region
West
Developer
PacifiCorp Energy Supply Management
IA Status
IA Executed

BetaActiveSolarPacifiCorpLBNL

178 MW generation in Emery, UT · In queue since November 2016 · Proposed COD June 2019

178 MW

Capacity

1

Components

Solar

9y 4m

In Queue

IA Executed

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

2y 7m

Schedule

82 months past proposed COD

Construction75%
Queue EntryNov 15, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2019-06-30

Project Details

State

UT

County

Emery

Region

West

Developer

PacifiCorp Energy Supply Management

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Emery substation

Data Source

LBNL

No news available for this project.