178 MW generation in Emery, UT · In queue since November 2016 · Proposed COD June 2019
178 MW
Capacity
1
Components
Solar
9y 4m
In Queue
IA Executed
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
2y 7m
Schedule
82 months past proposed COD
Construction75%
Queue EntryNov 15, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2019-06-30
Project Details
State
UT
County
Emery
Region
West
Developer
PacifiCorp Energy Supply Management
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Emery substation
Data Source
LBNL
No news available for this project.