BetaSuspendedSolarPacifiCorpLBNL
30 MW generation in Sanpete, UT · In queue since November 2016 · Proposed COD February 2018
30 MW
Capacity
1
Components
Solar
9y 4m
In Queue
Suspended
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
1y 3m
Suspended38%
Queue EntryNov 15, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2018-02-22
Project Details
State
UT
County
Sanpete
Region
West
Developer
PacifiCorp Energy Supply Management
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Gunnison-Sigurd #1 transmission line
Data Source
LBNL
No news available for this project.