BetaActiveSolarPacifiCorpLBNL
20 MW generation in Emery, UT · In queue since November 2016 · Proposed COD February 2020
20 MW
Capacity
1
Components
Solar
9y 4m
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3y 3m
Schedule
75 months past proposed COD
Construction75%
Queue EntryNov 7, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2020-02-01
Project Details
State
UT
County
Emery
Region
West
Developer
Pivot 13, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Moore substation
Data Source
LBNL
No news available for this project.