— Project Summary

Queue ID
PacifiCorp-805
Capacity
95 MW
Technology
Solar
Status
active
Location
Kane, UT
Region
West
Developer
Glen Canyon Solar A, LLC
IA Status
Suspended

BetaActiveSolarPacifiCorpLBNL

95 MW generation in Kane, UT · In queue since September 2016 · Proposed COD December 2019

95 MW

Capacity

1

Components

Solar

9y 6m

In Queue

Suspended

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

3y 3m

Schedule

76 months past proposed COD

In Study38%
Queue EntrySep 30, 2016

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-12-19

Project Details

State

UT

County

Kane

Region

West

Developer

Glen Canyon Solar A, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Sigurd-Glen Canyon transmission line

Data Source

LBNL