80 MW hybrid in Carbon, UT · In queue since September 2016 · Proposed COD December 2019
80 MW
Capacity
1
Components
Solar
9y 6m
In Queue
IA Executed
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
3y 3m
Schedule
77 months past proposed COD
Construction75%
Queue EntrySep 1, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2019-12-01
Project Details
State
UT
County
Carbon
Region
West
Developer
RC Solar Energy LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Mathington substation
Data Source
LBNL
No news available for this project.