BetaActiveSolarBatteryPacifiCorpLBNL
74.9 MW hybrid in Fremont, WY · In queue since August 2016 · Proposed COD September 2019
74.9 MW
Capacity
1
Components
Solar
9y 7m
In Queue
IA Executed
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
3y 1m
Schedule
79 months past proposed COD
Construction75%
Queue EntryAug 8, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2019-09-30
Project Details
State
WY
County
Fremont
Region
West
Developer
Fresh Air Energy II, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Riverton-Thermopolis transmission line
Data Source
LBNL