— Project Summary

Queue ID
PacifiCorp-787
Capacity
400 MW
Technology
Solar+Battery
Status
active
Location
Emery, UT
Region
West
Developer
Green River Solar I, LLC
IA Status
IA Executed

BetaActiveSolarBatteryPacifiCorpLBNL

400 MW hybrid in Emery, UT · In queue since August 2016 · Proposed COD November 2018

400 MW

Capacity

1

Components

Solar

9y 7m

In Queue

IA Executed

IA Status

COD target: 2018

Interconnection Timeline

Total Duration

2y 3m

Schedule

90 months past proposed COD

Construction75%
Queue EntryAug 8, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2018-11-15

Project Details

State

UT

County

Emery

Region

West

Developer

Green River Solar I, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Emery-Sigurd #2 line

Data Source

LBNL

No news available for this project.