BetaActiveWindPacifiCorpLBNL
100 MW generation in Summit, UT · In queue since August 2016 · Proposed COD December 2018
100 MW
Capacity
1
Components
Wind
9y 7m
In Queue
IA Executed
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2y 4m
Schedule
88 months past proposed COD
Construction75%
Queue EntryAug 4, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2018-12-31
Project Details
State
UT
County
Summit
Region
West
Developer
Echo Divide Wind, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Evanston-Anschutz transmission line
Data Source
LBNL
No news available for this project.