— Project Summary

Queue ID
PacifiCorp-786
Capacity
100 MW
Technology
Wind
Status
active
Location
Summit, UT
Region
West
Developer
Echo Divide Wind, LLC
IA Status
IA Executed

BetaActiveWindPacifiCorpLBNL

100 MW generation in Summit, UT · In queue since August 2016 · Proposed COD December 2018

100 MW

Capacity

1

Components

Wind

9y 7m

In Queue

IA Executed

IA Status

COD target: 2018

Interconnection Timeline

Total Duration

2y 4m

Schedule

88 months past proposed COD

Construction75%
Queue EntryAug 4, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2018-12-31

Project Details

State

UT

County

Summit

Region

West

Developer

Echo Divide Wind, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Evanston-Anschutz transmission line

Data Source

LBNL

No news available for this project.