— Project Summary

Queue ID
PacifiCorp-783
Capacity
30 MW
Technology
Solar+Battery
Status
active
Location
Natrona, WY
Region
West
Developer
Dinosolar, LLC
IA Status
IA Executed

BetaActiveSolarBatteryPacifiCorpLBNL

30 MW hybrid in Natrona, WY · In queue since August 2016 · Proposed COD June 2020

30 MW

Capacity

1

Components

Solar

9y 7m

In Queue

IA Executed

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

3y 10m

Schedule

70 months past proposed COD

Construction75%
Queue EntryAug 3, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2020-06-30

Project Details

State

WY

County

Natrona

Region

West

Developer

Dinosolar, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Bar Nunn substation

Data Source

LBNL

No news available for this project.