80 MW generation in Tooele, UT · In queue since August 2016 · Proposed COD December 2018
80 MW
Capacity
1
Components
Solar
9y 7m
In Queue
IA Executed
IA Status
Signed Oct 2018
Interconnection Timeline
Queue → IA
2y 2m
IA → COD
2 months
Total Duration
2y 2m
Schedule
88 months past proposed COD
Construction75%
Queue EntryAug 1, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementOct 2, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2018-12-31
Project Details
State
UT
County
Tooele
Region
West
Developer
Elektron Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Craner Flat substation