BetaActiveSolarBatteryPacifiCorpLBNL
80 MW hybrid in Box Elder, UT · In queue since May 2016 · Proposed COD December 2018
80 MW
Capacity
1
Components
Solar
9y 10m
In Queue
IA Executed
IA Status
Signed Jun 2018
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
6 months
Total Duration
2y 1m
Schedule
88 months past proposed COD
Construction75%
Queue EntryMay 25, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementJun 28, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2018-12-31
Project Details
State
UT
County
Box Elder
Region
West
Developer
Steel Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Wheelon-Nucor transmission line
Data Source
LBNL
No news available for this project.