— Project Summary

Queue ID
PacifiCorp-741
Capacity
40 MW
Technology
Solar
Status
suspended
Location
Klamath, OR
Region
West
Developer
Aurora Solar, LLC
IA Status
Suspended

BetaSuspendedSolarPacifiCorpLBNL

40 MW generation in Klamath, OR · In queue since May 2016 · Proposed COD September 2018

40 MW

Capacity

1

Components

Solar

9y 10m

In Queue

Suspended

IA Status

Signed Dec 2017

Interconnection Timeline

Queue → IA

1y 7m

IA → COD

9 months

Total Duration

1y 7m

Suspended38%
Queue EntryMay 6, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementDec 6, 2017

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2018-09-01

Project Details

State

OR

County

Klamath

Region

West

Developer

Aurora Solar, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Klamath Falls-Lone Pine 230 kV transmission line

Data Source

LBNL

No news available for this project.