55 MW hybrid in Crook, OR · In queue since March 2016 · Proposed COD July 2018
55 MW
Capacity
1
Components
Solar
10 years
In Queue
IA Executed
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2y 4m
Schedule
94 months past proposed COD
Construction75%
Queue EntryMar 4, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2018-07-01
Project Details
State
OR
County
Crook
Region
West
Developer
Prineville Solar Energy LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Baldwin Rd Ponderosa transmission line
Data Source
LBNL
No news available for this project.