BetaSuspendedOther StoragePacifiCorpLBNL
415.8 MW storage in Klamath, OR · In queue since July 2015 · Proposed COD December 2022
415.8 MW
Capacity
1
Components
Other Storage
10y 8m
In Queue
Suspended
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
7y 5m
Suspended38%
Queue EntryJul 28, 2015
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
OR
County
Klamath
Region
West
Developer
Swan Lake North Hydro, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
PacifiCorp's Malin 500 kV substation
Data Source
LBNL
No news available for this project.