BetaActiveSolarBatteryPacifiCorpLBNL
58 MW hybrid in Iron, UT · In queue since February 2015 · Proposed COD October 2016
58 MW
Capacity
1
Components
Solar
11y 1m
In Queue
Suspended
IA Status
Signed Sep 2016
Interconnection Timeline
Queue → IA
1y 7m
IA → COD
1 month
Total Duration
1y 7m
Schedule
115 months past proposed COD
Construction38%
Queue EntryFeb 9, 2015
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementSep 8, 2016
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2016-10-01
Project Details
State
UT
County
Iron
Region
West
Developer
Parowan Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Parowan substation
Data Source
LBNL
No news available for this project.