BetaActiveSolarPacifiCorpLBNL
99 MW generation in Iron, UT · In queue since December 2014 · Proposed COD December 2016
99 MW
Capacity
1
Components
Solar
11y 3m
In Queue
IA Executed
IA Status
Signed Sep 2016
Interconnection Timeline
Queue → IA
1y 9m
IA → COD
3 months
Total Duration
1y 9m
Schedule
112 months past proposed COD
Construction75%
Queue EntryDec 3, 2014
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementSep 9, 2016
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2016-12-31
Project Details
State
UT
County
Iron
Region
West
Developer
Rush Lake Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Parowan-West Cedar line
Data Source
LBNL
No news available for this project.