BetaActiveSolarPacifiCorpLBNL
99 MW generation in Beaver, UT · In queue since November 2014 · Proposed COD December 2016
99 MW
Capacity
1
Components
Solar
11y 4m
In Queue
IA Executed
IA Status
Signed Sep 2016
Interconnection Timeline
Queue → IA
1y 10m
IA → COD
3 months
Total Duration
1y 10m
Schedule
112 months past proposed COD
Construction75%
Queue EntryNov 20, 2014
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementSep 9, 2016
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2016-12-31
Project Details
State
UT
County
Beaver
Region
West
Developer
Fremont Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Parowan-Sigurd line
Data Source
LBNL