BetaActiveHydroPacifiCorpLBNL
0.9 MW generation in Bannock, ID · In queue since October 2019 · Proposed COD May 2020
0.9 MW
Capacity
1
Components
Hydro
6y 5m
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
7 months
Schedule
72 months past proposed COD
Construction75%
Queue EntryOct 23, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2020-05-01
Project Details
State
ID
County
Bannock
Region
West
Developer
Commercial Energy Management, Inc.
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit LAV11 out of Lava substation
Data Source
LBNL
No news available for this project.