2.99 MW generation in Umatilla, OR · In queue since July 2018 · Proposed COD December 2019
2.99 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
1y 5m
Schedule
76 months past proposed COD
Construction75%
Queue EntryJul 5, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2019-12-31
Project Details
State
OR
County
Umatilla
Region
West
Developer
Pilot Rock Solar 2, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit 5W406 out of Pilot Rock substation
Data Source
LBNL