Malta Project — Project Summary

Queue ID
OUC-202311
Capacity
225 MW
Technology
Battery
Status
active
Location
Brevard, FL
Region
Southeast
Developer
IA Status
Facility Study

Malta Project

BetaActiveBatteryOUCLBNL

225 MW storage in Brevard, FL · In queue since March 2023 · Proposed COD December 2026

225 MW

Capacity

1

Components

Battery

3 years

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 9m

Facilities Study50%
Queue EntryMar 6, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-30

Project Details

State

FL

County

Brevard

Region

Southeast

Developer

Utility

Orlando Utilities Commission

Entity

OUC

Point of Interconnection

OUC Indian River Plant

Data Source

LBNL