Bull Creek (Osceola Generating Station)
BetaActiveGasOUCLBNL
555 MW generation in Osceola, FL · In queue since September 2021 · Proposed COD June 2025
555 MW
Capacity
1
Components
Gas
4y 6m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 9m
Schedule
10 months past proposed COD
Construction75%
Queue EntrySep 28, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
FL
County
Osceola
Region
Southeast
Developer
—
Utility
Orlando Utilities Commission
Entity
OUC
Point of Interconnection
Rocky Pond
Data Source
LBNL
No news available for this project.