Arthur Kill Unit 2 Uprate
BetaActiveGasNYISOLBNL + Live
369.9 MW generation in Richmond, NY · In queue since October 2024 · Proposed COD May 2025
369.9 MW
Capacity
1
Components
Gas
1y 5m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
7 months
Schedule
11 months past proposed COD
Pre-Study0%
Queue EntryOct 4, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-05-01
Project Details
State
NY
County
Richmond
Region
NYISO
Developer
Arthur Kill Power LLC
Utility
ConEd
Entity
NYISO
Point of Interconnection
Freshkills 138kV
Data Source
LBNL + Live