West Babylon Internal Combustion (IC), Unit 4
BetaActiveOilNYISOLBNL + Live
49 MW generation in Suffolk, NY · In queue since September 2024
49 MW
Capacity
1
Components
Oil
1y 6m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1y 6m
Pre-Study0%
Queue EntrySep 27, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
Suffolk
Region
NYISO
Developer
National Grid Generation, LLC
Utility
LIPA
Entity
NYISO
Point of Interconnection
West Babylon 13.8 kV
Data Source
LBNL + Live
No news available for this project.