Azalea Wind 2
BetaActiveWindNYISOLBNL + Live
50 MW generation in Schuyler, NY · In queue since October 2024 · Proposed COD December 2029
50 MW
Capacity
1
Components
Wind
1y 5m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 2m
Pre-Study0%
Queue EntryOct 15, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-01
Project Details
State
NY
County
Schuyler
Region
NYISO
Developer
Azalea Wind LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Montour Falls to Coddington Road 115kV
Data Source
LBNL + Live
No news available for this project.