Lewis Wind — Project Summary

Queue ID
NYISO-C24-367
Capacity
100 MW
Technology
Wind
Status
active
Location
Lewis, NY
Region
NYISO
Developer
Lewis Wind, LLC
IA Status

Lewis Wind

BetaActiveWindNYISOLBNL

100 MW generation in Lewis, NY · In queue since October 2024 · Proposed COD December 2030

100 MW

Capacity

1

Components

Wind

1y 5m

In Queue

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6y 2m

Pre-Study0%
Queue EntryOct 15, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-01

Project Details

State

NY

County

Lewis

Region

NYISO

Developer

Lewis Wind, LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Volney-Marcy Line 19 345kV line

Data Source

LBNL