Hickling Storage, LLC
BetaActiveBatteryNYISOLBNL
90 MW storage in Steuben, NY · In queue since October 2024 · Proposed COD December 2027
90 MW
Capacity
1
Components
Battery
1y 5m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 2m
Pre-Study0%
Queue EntryOct 14, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
NY
County
Steuben
Region
NYISO
Developer
Hickling Storage, LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
115kV Hickling Substation
Data Source
LBNL
No news available for this project.