Little Falls Solar — Project Summary

Queue ID
NYISO-C24-347
Capacity
78 MW
Technology
Solar
Status
active
Location
Herkimer, NY
Region
NYISO
Developer
Hodson Energy Little Falls LLC
IA Status

Little Falls Solar

BetaActiveSolarNYISOLBNL

78 MW generation in Herkimer, NY · In queue since October 2024 · Proposed COD February 2028

78 MW

Capacity

1

Components

Solar

1y 5m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 4m

Pre-Study0%
Queue EntryOct 14, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-02-01

Project Details

State

NY

County

Herkimer

Region

NYISO

Developer

Hodson Energy Little Falls LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Watkins Road-Inghams Line 2 115kV

Data Source

LBNL