AGR NY1 — Project Summary

Queue ID
NYISO-C24-343
Capacity
1229 MW
Technology
Offshore Wind
Status
active
Location
Nassau, NY
Region
NYISO
Developer
Avangrid Renewables, LLC
IA Status

AGR NY1

BetaActiveOffshore WindNYISOLBNL

1,229 MW generation in Nassau, NY · In queue since October 2024 · Proposed COD June 2033

1,229 MW

Capacity

1

Components

Offshore Wind

1y 5m

In Queue

IA Status

COD target: 2033

Interconnection Timeline

Total Duration

8y 8m

Pre-Study0%
Queue EntryOct 11, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2033-06-01

Project Details

State

NY

County

Nassau

Region

NYISO

Developer

Avangrid Renewables, LLC

Utility

NYPA

Entity

NYISO

Point of Interconnection

East Garden City 345 kV

Data Source

LBNL