AGRE Storage — Project Summary

Queue ID
NYISO-C24-342
Capacity
125 MW
Technology
Battery
Status
active
Location
Queens, NY
Region
NYISO
Developer
Beacon Wind LLC
IA Status

AGRE Storage

BetaActiveBatteryNYISOLBNL

125 MW storage in Queens, NY · In queue since October 2024 · Proposed COD May 2029

125 MW

Capacity

1

Components

Battery

1y 5m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 7m

Pre-Study0%
Queue EntryOct 11, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-01

Project Details

State

NY

County

Queens

Region

NYISO

Developer

Beacon Wind LLC

Utility

ConEd

Entity

NYISO

Point of Interconnection

Astoria West 138 kV

Data Source

LBNL

No news available for this project.