AGRE Storage
BetaActiveBatteryNYISOLBNL
125 MW storage in Queens, NY · In queue since October 2024 · Proposed COD May 2029
125 MW
Capacity
1
Components
Battery
1y 5m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 7m
Pre-Study0%
Queue EntryOct 11, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-01
Project Details
State
NY
County
Queens
Region
NYISO
Developer
Beacon Wind LLC
Utility
ConEd
Entity
NYISO
Point of Interconnection
Astoria West 138 kV
Data Source
LBNL
No news available for this project.