Chateauguay BESS
BetaActiveBatteryNYISOLBNL
200 MW storage in Greene, NY · In queue since October 2024 · Proposed COD December 2028
200 MW
Capacity
1
Components
Battery
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntryOct 10, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
NY
County
Greene
Region
NYISO
Developer
Capital Region Energy Storage LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Leeds 345kV
Data Source
LBNL
No news available for this project.