Aria Storage 2 — Project Summary

Queue ID
NYISO-C24-338
Capacity
150 MW
Technology
Battery
Status
active
Location
Dutchess, NY
Region
NYISO
Developer
Terra-Gen Development, LLC
IA Status

Aria Storage 2

BetaActiveBatteryNYISOLBNL + Live

150 MW storage in Dutchess, NY · In queue since October 2024 · Proposed COD December 2028

150 MW

Capacity

1

Components

Battery

1y 5m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 2m

Pre-Study0%
Queue EntryOct 10, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

NY

County

Dutchess

Region

NYISO

Developer

Terra-Gen Development, LLC

Utility

ConEd

Entity

NYISO

Point of Interconnection

East Fishkill 345 kV

Data Source

LBNL + Live

No news available for this project.