Aria Storage 1
BetaActiveBatteryNYISOLBNL + Live
100 MW storage in Dutchess, NY · In queue since October 2024 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntryOct 10, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
NY
County
Dutchess
Region
NYISO
Developer
Terra-Gen Development, LLC
Utility
ConEd
Entity
NYISO
Point of Interconnection
East Fishkill 345 kV substation
Data Source
LBNL + Live
No news available for this project.