Pouch Energy Storage System — Project Summary

Queue ID
NYISO-C24-333
Capacity
47.1 MW
Technology
Battery
Status
active
Location
Kings, NY
Region
NYISO
Developer
the NY Power Authority
IA Status

Pouch Energy Storage System

BetaActiveBatteryNYISOLBNL + Live

47.1 MW storage in Kings, NY · In queue since October 2024 · Proposed COD December 2030

47.1 MW

Capacity

1

Components

Battery

1y 5m

In Queue

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6y 2m

Pre-Study0%
Queue EntryOct 9, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-01

Project Details

State

NY

County

Kings

Region

NYISO

Developer

the NY Power Authority

Utility

ConEd

Entity

NYISO

Point of Interconnection

Fox Hills 138kV Substation

Data Source

LBNL + Live