Stoner Trail Storage
BetaActiveBatteryNYISOLBNL
100 MW storage in Fulton, NY · In queue since October 2024 · Proposed COD August 2028
100 MW
Capacity
1
Components
Battery
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 10m
Pre-Study0%
Queue EntryOct 9, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-01
Project Details
State
NY
County
Fulton
Region
NYISO
Developer
Granada Solar, LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Inghams-Stoner 115kV line 9 and Meco-Maple Ave 115kV line 22
Data Source
LBNL