WEB Addison Solar
BetaActiveSolarNYISOLBNL
100 MW generation in Steuben, NY · In queue since October 2024 · Proposed COD June 2028
100 MW
Capacity
1
Components
Solar
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 8m
Pre-Study0%
Queue EntryOct 8, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
NY
County
Steuben
Region
NYISO
Developer
SWEB Development USA LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Stony Ridge - Sullivan Park 115 kV
Data Source
LBNL